HAKI ENGINEERS TEMPORARY ACCESS SOLUTION FOR PEDESTRIAN TUNNEL 

 

Contracted to help build the Køge Nord station near Copenhagen, Denmark, Barberens Stilladser A/S required a challenging access solution that would cover an entire pedestrian tunnel. 

With the tunnel being situated over the busy Sydmotorvejen motorway, it was imperative that any scaffold structure used was extremely safe. 

 

HAKI offered a solution to Barberens Stilladser A/S using the Universal system, in particular the puncheon and beam rider. These components have been indispensable to the project, providing the adaptability required to get around the tunnel, and ultimately secured us the job. 

 

HAKI is now continuing to work with Barberens Stilladser A/S until project completion in Summer 2019. 